Background By Dr. Maximilian Mandl 10 min read

Hutter's Falter answer on Szombathely and the Hungarian expert opinion

Hans-Peter Hutter's Falter answer on Szombathely next to the Hungarian expert opinion: which lab measured which values, and what is documented on the gravel's origin.

On 26 May 2026, Falter (issue 22/2026, interview by Matthias Winterer) published a conversation with Assoz. Prof. PD DI Dr. Hans-Peter Hutter, head of the Land Burgenland task force "Vorsorgeabklärung Luftqualität", in which he comments on the asbestos contamination in the Hungarian city of Szombathely. Here his answer is set next to the Hungarian expert opinion the high readings come from, and next to what is documented about the origin of the gravel.

The question and the answer

Falter put the question like this:

„Die ungarische Stadt Szombathely will den Gesundheitsnotstand ausrufen. In einer Wohnsiedlung liegt Asbestschotter, wahrscheinlich aus dem Burgenland. Wird der Skandal in Österreich verharmlost?"

In English: the Hungarian city of Szombathely intends to declare a health emergency; asbestos gravel, probably from Burgenland, lies in a residential area; is the scandal being played down in Austria?

Hutter's answer:

„Das ist eine berechtigte Frage, obwohl nicht geklärt ist, ob dieser Schotter tatsächlich aus dem Burgenland stammt. Unser Messtechniker kann die hohen Werte von Asbestfasern in der Umgebungsluft vor Ort, die ein ungarisches Labor gemessen hat, nicht nachvollziehen. Er selbst hat in Szombathely deutlich niedrigere Werte gemessen. Werte von bis zu 300.000 Fasern pro Kubikmeter Luft gibt es eigentlich nur in Steinbrüchen, wo asbesthaltiges Material zerkleinert wird. Wenn ein Bürgermeister solche Zahlen auf den Tisch bekommt, gerät er natürlich in Panik. Da muss er handeln. Wir halten sie aber nicht für realistisch."

In English: that is a legitimate question, although it has not been clarified whether this gravel actually comes from Burgenland; our measurement technician cannot make sense of the high airborne asbestos fibre values that a Hungarian laboratory measured on site; he himself measured significantly lower values in Szombathely; values of up to 300,000 fibres per cubic metre really only occur in quarries where asbestos-bearing material is crushed; when a mayor is handed such figures, he naturally panics and has to act; but we do not consider them realistic.

The laboratory and the values

The high values Hutter refers to come from an expert opinion that the Hungarian firm KÖR-KER Kft. prepared for the Vas county government office (Vas Vármegyei Kormányhivatal), dated 8 April 2026 and published by the county office with its announcement of 13 April 2026. In its release of 14 April 2026, Greenpeace points to this document as the „Originalquelle der Messwerte" (original source of the readings) and states: „Die Messungen wurden unter Beteiligung des gleichen Labors, das auch für das Land Burgenland aktiv ist, durchgeführt." (the measurements were carried out with the participation of the same laboratory that is also active for the Land Burgenland). According to the opinion, KÖR-KER brought in the Vienna firm ESW Consulting WRUSS Ziviltechnikergesellschaft (p. 2), the firm that also measured for the task force: at the task force's air measurements in Oberwart, per ORF Burgenland (2 February 2026), „der Ziviltechniker Hakan Kuleci von der Firma ESW Consulting WRUSS" (the civil engineer Hakan Kuleci of ESW Consulting WRUSS) explained the measuring equipment.

The opinion does, however, record who measured which value. On 4 March 2026, WRUSS and KÖR-KER took air samples at the same two points on Síp utca, a gravel road in the Oladi Plató residential area, WRUSS with accreditation and KÖR-KER without (pp. 5 f.). The opinion states this for the individual samples and analyses, not for the laboratories as such: it lists both laboratories with an accreditation number (p. 2). For KÖR-KER it marks the analyses of material samples by polarised light and phase contrast microscopy as with accreditation (pp. 3 to 5), but the analysis of one material sample by scanning electron microscopy and all of this laboratory's air samples as without accreditation (pp. 4 to 7). Twenty-four hours were planned for that day; after about three hours precipitation set in, which according to the opinion washed dust and asbestos fibres out of the air, and the samples from before the precipitation were evaluated. WRUSS determined 34,809 and 41,711 fibres per cubic metre, KÖR-KER 37,600 and 43,600 at the same points (p. 6).

On 24 March both laboratories repeated the sampling at the same points. By then the area had dried out, and the 24-hour samples were overloaded with dust and could not be evaluated (pp. 5 to 7). What remained evaluable were two one-hour samples that KÖR-KER additionally took, again without accreditation, in front of Síp utca 70, in the opinion's words „Az érintett útszakasz kiemelt használata mellett" (with increased use of the road section concerned): 292,100 fibres per cubic metre by scanning electron microscopy and 208,000 by phase contrast microscopy (pp. 7 f.).

The values "up to 300,000" in Hutter's answer correspond to the rounded peak of 292,100. That value and the second high one, 208,000, were measured by KÖR-KER, a Hungarian laboratory. The laboratory that also measured for the Land was involved in the investigation; its values from 4 March are well below the peak, and so are the values KÖR-KER determined on the same day at the same points. Whom Hutter means by „Unser Messtechniker" (our measurement technician), and whether his „deutlich niedrigere Werte" (significantly lower values) are those of WRUSS, the interview does not say. We have not found a publication of a task force measurement in Szombathely (searched on 20 October 2026 on the Land's task force page and in its table of readings of 7 July 2026).

Hutter says values of this height occur „eigentlich nur in Steinbrüchen" (really only in quarries), and he does not consider the figures realistic. The opinion interprets the same one-hour values differently: as peak concentrations that arise with vehicle traffic raising a lot of dust and expose road users considerably even within a short time (p. 8).

On the order of magnitude: Greenpeace speaks of „sieben Messungen mit Messergebnissen zwischen mindestens 35.000 und 292.000 Fasern pro Kubikmeter" (seven measurements with results between at least 35,000 and 292,000 fibres per cubic metre). The opinion contains six evaluable air values; the lowest, 34,809, is just below 35,000. As its yardstick it names the Hungarian limit value for asbestos in ambient air, 1,000 fibres per cubic metre as a 24-hour and as an annual mean (4/2011. (I. 14.) VM rendelet, Annex 1, point 1.1.4.2). Against it, the opinion assesses the two values that WRUSS determined with accreditation on 4 March and the one-hour values of 24 March. For 34,809 and 41,711 it notes that they are means over about three hours and that, because the sampling was interrupted, a full 24-hour assessment under the regulation is not possible; referred to 24 hours, however, they would still amount to a multiple of the limit value. Of the one-hour value of 292,100 it writes that it exceeds the limit value considerably, and it calls the 208,000 by phase contrast microscopy a similar result (p. 8). The task force uses the same figure, 1,000 fibres per cubic metre, as the reference value for its measurements (Land Burgenland, task force page).

Greenpeace environmental chemist Herwig Schuster attributed the difference between Hungarian and Burgenland values to the fact that the Hungarian measurements had been „bei trockenem Wetter unter Realbedingungen durchgeführt" (carried out in dry weather under real conditions), while the Land Burgenland was resting „auf den letzten Messergebnissen aus dem Winter" (on its last results from winter) (Greenpeace, 14 April 2026). His comparison concerns the Land's winter measurements in Burgenland, not the measurement in Szombathely that Hutter refers to.

The origin

Falter asked about gravel "probably from Burgenland"; Hutter answered that it is "not clarified" whether "this gravel actually comes from Burgenland". Both phrasings, "probably" and "not clarified", concern the attribution of this one specific batch of gravel sampled in Szombathely.

What is publicly documented is the broader trade route. In response to a data request by Martin Németh, a member of the municipal council of Bük, the Hungarian tax and customs authority NAV released data from its road freight control system. They show to which Hungarian addresses deliveries were made since 2015 from the four closed Burgenland quarries, Pilgersdorf, Bernstein, Rumpersdorf (Glashütten) and Badersdorf, and name more than 250 municipalities (HVG, 23 May 2026; G7/Telex, 27 May 2026). G7/Telex gives a different figure from the foreign trade statistics: between 1998 and 2025, around 2.8 million tonnes of stone and gravel were delivered from Austrian quarries to Hungary; this figure covers imports from Austria as a whole, not the four quarries.

The freight data show goods movements and first destinations of material from the four quarries. According to the express caveat of the person who requested them, they do not prove that asbestos-bearing material reached each of these places (HVG), and they also do not show from which quarry the stones of this one Szombathely road come. For the specific material, the Vas county office speaks of gravel „osztrák eredetű" (of Austrian origin), and the mayor of deliveries from Austrian quarries (Vas county office, 13 April 2026); Greenpeace attributes it to Burgenland. We have not found an independent forensic attribution of the individual batch to a quarry in the sources checked; the documented trade route makes a Burgenland origin plausible.

Timeline

  • 4 and 24 March 2026: Air measurements on Síp utca in Szombathely: on 4 March by WRUSS (34,809 and 41,711 fibres per cubic metre) and KÖR-KER (37,600 and 43,600); on 24 March again by both laboratories, whose 24-hour samples were overloaded with dust and could not be evaluated, plus two one-hour samples by KÖR-KER (292,100 and 208,000) (KÖR-KER opinion, 8 April 2026).
  • 13 April 2026: The Vas county office publishes the opinion. The city and the county office state that they are treating the situation as a health emergency; the city council applies to the government for a formal declaration on 21 April (Savaria Fórum, 13 and 21 April 2026).
  • 14 April 2026: Greenpeace reports values between 35,000 and 292,000 fibres per cubic metre from the opinion and states that the laboratory that is also active for the Land was involved (Greenpeace).
  • 26 May 2026: Falter publishes the interview: the origin of the specific batch is "not clarified", and the high values are "not considered realistic".

Note

Hans-Peter Hutter's position is represented by his statements in the Falter interview (issue 22/2026); the quoted question and answer are reproduced in full. We check the readings against the Hungarian opinion itself, which Greenpeace gives as its source; assessments that come only from Greenpeace, an organisation with a stake in the matter, are flagged as such. We are not uninvolved either: ungiftig.at is a consultancy for building pollutants that also works in Burgenland, and in April 2026 it put written questions to Hutter as head of the task force about one of the task force's recommendations and about its reference value of 1,000 fibres per cubic metre, most recently in an open letter. Should any point presented here be demonstrably incorrect, we will correct it.

Sources

Questions on the topic? → Contact

Let's talk about your building

Write to us or call.

Send a message

We'll get back to you within one business day.

Free

Direct line

The fastest way to reach us is usually in writing, by email. Prefer to talk your project through on the phone? Call us and we'll work out together which service fits and plan the next steps.

Free

Price calculator

Combine inspection, samples and travel and see the approximate cost immediately.

Estimate costs